Please join Dr. Baeta on Thanksgiving Day, Thursday, November 24 at 9:30 AM at Adams Field (NHS) as we celebrate the opening of the new Athletic Complex.
The Athletic Complex has reached one of four final milestones. This week the Multipurpose Field has reached substantial completion. Substantial completion means that we can practice and play on the site. However, this is still a work-site and we are currently only allowing for NHS athletes to use the field.
The Norton HS Track and Field will not be at substantial completion until the end of the month. If we have any practices or games on the field before the track is substantially complete it will NOT be covered by the warranty. I cannot allow for the warranty to become voided. I know it is frustrating, but these are the facts. Once we get substantial completion on the Track and Field then we can utilize it.
The third milestone is the Tennis Courts area. We anticipate that this will not be completed until the spring of 2023 due to painting.
The final milestone is the project close-out which is scheduled for December, not including the Tennis Courts painting. The other remaining items to be completed in December are the scoreboards, which are on backorder.
Please note that these fields are not open to the public at this time as they are still construction sites.
Multipurpose Field & Tennis Courts
NHS Stadium Field & Track
Multipurpose Field & Tennis Courts:
NHS Stadium Field & Track:
Multipurpose Field & Tennis Courts
NHS Stadium Field & Track
Multipurpose Field & Tennis Courts:
NHS Stadium Field & Track:
Multipurpose Field & Tennis Courts
NHS Stadium Field & Track
The turf installation is scheduled to begin with the NHS Stadium Field the week of August 8.
Multipurpose Field
NHS Stadium Field & Track
This month construction has been focused on drainage utility and electrical installation.
The turf installation is on schedule to begin August 1.
Multipurpose Field
NHS Stadium Field & Track
Initial construction began week of May 16-20, 2022, which included:
During May 23-May 30 work included:
Multipurpose Field
March 2022 Bid Document
Athlectic Complex November 2021 Updated
Option A
Printable Schematic
Printable Complete Financials
Option B
Printable Schematic
Printable Complete Financials
Option C
Printable SchematicPrintable Complete Financials
Option D
Printable Schematic
Printable Complete Financials
Option E
Printable Schematic
Printable Complete Financials
Option F-1
Printable Schematic
Printable Complete Financials
Option F-2
Printable Schematic
Printable Complete Financials
Option G
Printable Schematic
Printable Complete Financials
Option H